Loading...
Quick Links

Reply To: Null in Baseline Cost on Summary Task

Home Forums Discussion Null in Baseline Cost on Summary Task Reply To: Null in Baseline Cost on Summary Task

#409404

I discovered this issue when I installed forProject for DCMA 14-pt assessment and it errored. I entered a 0 in the field per the advise of the forProject rep and now the application runs fine. I was just trying to figure out if anybody had any clue how this could have happened in the first place. The company rep did say he had one other client with this issue prior. For the record, I never enter data into baseline fields – I always use the “Set Baseline” feature. So I couldn’t figure out how this issue occurred.