Home › Forums › Discussion › Look ahead report › Reply To: Look ahead report
You may also want to consider executing this report as a view and then printing it.
Project has an ability to ask for prompts in a filter. How to do this is explained in this MPUG article.
This article references 2013 so I hope this capability also exists in 2007.
https://www.mpug.com/articles/creating-custom-report-project-2013-weeks-tasks/
If you used this technique, when you open the view, you can have Project prompt you with “What is the start date:” and then prompt you with “What is the end date:”. You have total control of the text within the prompt and how many prompts you get (maybe you only need an end date prompt for example).
This method uses a filter so you’re not messing around with custom field calculations.