Reply To: Team Member cannot see a project in the project center

Home Forums Discussion Team Member cannot see a project in the project center Reply To: Team Member cannot see a project in the project center

#409538
John Murphy
Member

Daryl,

Thanks for the extra explanation … it made sense and helped.

Net, net … There were two issues … one was the project was assigned the wrong team (so it did not show up in the view for anyone) and the other was the PM not using an Enterprise Resource.

I fixed the team associated with the project and replaced the typed in resource with the Resource Enterprise one.

The resource then could see the project …

Thanks again and sorry for delay in responding,
John