Home Forums Discussion Gantt – sort by path Reply To: Gantt – sort by path

#409539
Ben
Guest

Larry, thanks for your response. The start date sort does make it easier, but it leaves a lot of dependencies a fair distance from one-another which leaves them hard to follow. I’ve not a quick way to assign the 50+ deliverables to the 1500 lines (up to 5 levels of WBS for each deliverable) without manually following through the paths. Is there any way to get MSP to find the last item in the chain as a calculation (i.e. not just highlighting the task paths on the Gantt)?