Reply To: How to set a Maximum Budget for a resource in MSP 2016

Home Forums Discussion How to set a Maximum Budget for a resource in MSP 2016 Reply To: How to set a Maximum Budget for a resource in MSP 2016

#409578
Sud Tiwari
Guest

Larry, yes I will be entering the actual hours consumed by the resource (designer) in the Plan. This is where I have reached so far – I have assigned the designer a budget of $5000 in the resource sheet. To do that, I had to put him as a “Cost” type resource. Now, my question is, can I still assign him hourly rate (say $65/hr) so that when he exceeds 77 hrs, I get a notification in Gantt chart that the designer has consumed his $5000 budget (77 hrs * $65/hr = $5005).