Reply To: How to set a Maximum Budget for a resource in MSP 2016

Home Forums Discussion How to set a Maximum Budget for a resource in MSP 2016 Reply To: How to set a Maximum Budget for a resource in MSP 2016

#409579
Larry Christofaro
Participant

Sud, I suggest setting him up as a work resource with a baseline work of 77 hrs. Baselines can be directly entered into the resource usage or sheet view. Then you can compare the resource work/actual work with the baseline. There are other ways but this is a simple solution. Does this help?