Reply To: How to set a Maximum Budget for a resource in MSP 2016

Home Forums Discussion How to set a Maximum Budget for a resource in MSP 2016 Reply To: How to set a Maximum Budget for a resource in MSP 2016

#409586
Sud Tiwari
Guest

Need another help – I am trying to show a Graphical Indicator for positive and negative work variance in my resource sheet. But I’m stuck because the formula only results in happy smiley for both positive and negative variance. I have created a custom field called “Progress” and set up a formula with [Progress = Baseline Work – Actual Work]. and then I have setup a Graphical Indicators with two tests:

Progress is ‘greater than or equal to’ value [0], show (happy smiley)
Progress is ‘less than’ value [0], show image (sad smiley)

However in both the variance cases, I only see the happy smiley (for both +ve and -ve variances), your help will be appreciated.