Sud Tiwari
Guest

Daryl – Customization field I am using is “resource type”. Data values in this field returns both +ve and -ve values but when I change it to graphical indicator, it only returns only one type of smiley. I tried changing sequence of tests, still doesn’t work.

Larry – the formula I am using is below. sorry the formula in my previous comment was mistakenly entered as ‘Actual Work’ instead of ‘Work’:-

Progress = [Baseline Work] – [work]

Test for ‘Progress Flag’:-
is greater than or equal to, Value(s) = 0, Image = 🙂
is less than, Value(s) = 0, image = 🙁

I hope this site allows images.

Thank you gentlemen for trying to help me.