Reply To: Adding random data field at top of MS Project chart

Home Forums Discussion Adding random data field at top of MS Project chart Reply To: Adding random data field at top of MS Project chart

#409607
Larry Christofaro
Participant

Not sure I understand your request as related to the timeline chart. If you are talking about the out of box Timeline view then you select the tasks that show here. If you are talking about a report chart, you can:
* Create a custom field that flags these tasks
* Create a filter that filters out these tasks
* Add that filter to your chart report
Hope that helps…