Reply To: Making Team Members Able to View ALL Projects on Project Online OR NOT

Home Forums Discussion Making Team Members Able to View ALL Projects on Project Online OR NOT Reply To: Making Team Members Able to View ALL Projects on Project Online OR NOT

#409657
John Murphy
Member

Sai,

Thanks for the replies.

I found that adding My Organization category to Team Member and checking off the following does what I want … TMs see ALL but can only add tasks or reassign tasks on projects where they are on the Project Team …

View Project Schedule in Project Web App
View Project Site
View Project Summary in Project Center

Thanks,
John