Reply To: Critical Path not showing

Home Forums Discussion Critical Path not showing Reply To: Critical Path not showing

#409663
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Insert Total Slack and since you mentioned Critical = No, you should see a positive slack across all tasks. Now, check if the last task has Start No Later Date constraint with constraint date set to date that is later than the finish date of the task; this will change the late start = constraint date creating a positive float – screen for your reference https://db.tt/82wRmUGkdA. Remove the constraint type and you should be able to see the critical path.