Max. Good question. I realize it’s being picky but just so that we are all on the same page…Booking Type is a Resource field, not a task field. The reason I’m saying this is to try using the Published field, which is a task level field. Set the Published field to NO for those tasks you don’t want an update. I believe this will work for you. Good luck…