Reply To: Default Schedule Options versus custom Project Calendar

Home Forums Discussion Default Schedule Options versus custom Project Calendar Reply To: Default Schedule Options versus custom Project Calendar

#409739
Larry Christofaro
Participant

Dave, yes to did exactly what you are supposed to. The reason for the default schedule settings is to translate what you key into the schedule. It uses these settings instead of the calendar depending on what you are doing. If you enter a task with a one month duration, Project knows how many days to assign. If you enter a resource and give him/her 1 week, Project knows how many hours to assign. Hope that helps…