Reply To: Default Schedule Options versus custom Project Calendar

Home Forums Discussion Default Schedule Options versus custom Project Calendar Reply To: Default Schedule Options versus custom Project Calendar

#409740

Thanks for your response Larry. So are you saying that, in effect, the Project Calendar will always be overridden by the default schedule settings?
If I leave the default settings at 8 hours per day, but change the Project Calendar to 7 hours per day, the work calculation will be based on the default of 8 hours per day. If I enter a task duration of 1 day it will be 8 hours in duration, even if the Project Calendar is set to a 7 hour work day.