Loading...
Quick Links

Reply To: Default Schedule Options versus custom Project Calendar

Home Forums Discussion Default Schedule Options versus custom Project Calendar Reply To: Default Schedule Options versus custom Project Calendar

#409741
Larry ChristofaroLarry Christofaro
Participant

Dave, I totally understand the confusion. Let me try some other examples. Some companies do 4×10 hour days. Some companies do 4×9’s and then a 4 hr Friday. When you say that a task is one day, which day are you telling Project to use? What if your weekly schedule changes? What if it’s swing shift, what about 50, 50, 20 hour weeks? Every month has a different number of working days, and in a 4×10 work week it’s even less. Project needs a consistent number to return an entry of 1 day, 1 week, 1 month…and the calendar doesn’t provide that consistency. Hope that helps…