Loading...
Quick Links

Reply To: 2013 Project Server / SharePoint / Exchange task integration question

Home Forums Discussion 2013 Project Server / SharePoint / Exchange task integration question Reply To: 2013 Project Server / SharePoint / Exchange task integration question

#409751
Larry ChristofaroLarry Christofaro
Participant

I should have explained this when I first answered your question because it always comes up. Publishing the project and publishing the tasks are different. The task Publish flag is strictly for task assignments. The project is still published and the scheduling still shows in the Project Center. Publish no for the tasks is just for publishing assignments to the team. So the question is: are they being picked up in mysite and Outlook syncs?