Reply To: MSP not baselining when I append to template from Excel

Home Forums Discussion MSP not baselining when I append to template from Excel Reply To: MSP not baselining when I append to template from Excel

#409761
Rose
Guest

Hi Larry, we managed to figure out the problem. It was linked to the resources and calendars that were already loaded into MSP file. One of the resources had the wrong calendar allocated to it, and for activities when the dates and times were not within the calendar times MSP would not baseline them. By allocating the correct calendar to the resource we were able to fix the problem. Thanks