Reply To: 2013 Project Server / SharePoint / Exchange task integration question

Home Forums Discussion 2013 Project Server / SharePoint / Exchange task integration question Reply To: 2013 Project Server / SharePoint / Exchange task integration question

#409836
Max Borenstein
Guest

Well Larry,
I spent a week changing all 100% tasks to “Unpublished” I our DEV envirnoment this worked as you had described and they did not sync with Outlook. Today we turned this one in our PRD environment and all tasks came over including those that are unpublished. Have you seen this before and do you have any recommendations?
Thanks!
Max