Reply To: MS Project 2016 – Updating Master projects containing sub=projects

Home Forums Discussion MS Project 2016 – Updating Master projects containing sub=projects Reply To: MS Project 2016 – Updating Master projects containing sub=projects

#409844

Hi Larry
I go to Project/Sub-Project then find my project and select the mode “Read-Only” and leave the “Lin to Project” checked.
This prevents the Program Manager from checking out all the sub-projects while they review the overall schedule.

However, as mentioned, the project update are not coming in.

Thanks…