Reply To: MS Project 2016 – Updating Master projects containing sub=projects

Home Forums Discussion MS Project 2016 – Updating Master projects containing sub=projects Reply To: MS Project 2016 – Updating Master projects containing sub=projects

#409851
Larry Christofaro
Participant

Interesting Norman. I’ve never used that read only feature before, but I did a quick test (created a master with one sub – read only, saved the master, opened / changed / and closed the sub, opened the master again…and the changes came through). So I’m kind of lost with what you have you test. Can you try a simple test similar to what I just did and see if you get the same results?