Reply To: Progress S Curve using activity duration only

Home Forums Discussion Progress S Curve using activity duration only Reply To: Progress S Curve using activity duration only

#409855
John OwenJohn Owen
Member

I would assign a dummy resource to all tasks at 100%. Then you can draw your s-curves based on that dummy resource. Call the resource something like ‘Days’.