Loading...
Quick Links

Reply To: moving work to weekends in project 2013

Home Forums Discussion moving work to weekends in project 2013 Reply To: moving work to weekends in project 2013

#409874

Yes, if for some reason the task can now occur on a weekday, you can simply remove the task level calendar and the task will now schedule based on the project calendar. If for some reason you need to have it available to schedule across all 7 days, enter the name of your seven day calendar and leave the “Scheduling ignores resource calendars” option checked.

Note, that if the task can only occur on a weekend as per my original answer, and over the course of the project, predecessor work delays the task so that it cannot occur on the originally planned weekend, it will automatically jump to the next weekend because of the weekend only calendar.