Reply To: Resources assignement, after update

Home Forums Discussion Resources assignement, after update Reply To: Resources assignement, after update

#409950
Larry ChristofaroLarry Christofaro
Participant

Alek, my first response has to be NO. CPI and SPI are highly dependent on accurate baselines and tracking actuals. Unless you have all that background and are willing to rebuild the project, you won’t have accurate EV values. You could create a going forward plan and begin the process if needed. That could give you going forward EV, but it wouldn’t include historical schedule.