Reply To: Estimating timeline when subtask duration is entered in HOURS

Home Forums Discussion Estimating timeline when subtask duration is entered in HOURS Reply To: Estimating timeline when subtask duration is entered in HOURS

#410091

Sud
Looking at your earlier note, I agree, the total Work hours should be 40. The only thing I can think of that would cause this number to jump up to 170 would be a resource directly assigned to the summary task with an estimate of 130 hours. If that’s the case, remove that resource assignment from the summary task.