Reply To: Project Outline, Summary tasks and subtasks jumping around (WBS Codes)

Home Forums Discussion Project Outline, Summary tasks and subtasks jumping around (WBS Codes) Reply To: Project Outline, Summary tasks and subtasks jumping around (WBS Codes)

#410146

Courtney;
You may also want to look to see if the view you are using is corrupted. I’ve hit scenarios where I can copy in a view, but I cannot paste. The cause is a corrupted table within the view. With your view open, go into tables, then more tables and with the current view table selected, click edit. If your view table is corrupted, you’ll see a table row that doesn’t specific an actual field name. It will have some form of an error on that row. (I can’t remember the exact phrasing, but it will be obvious) Anyway, delete that row from the table definition, save, and re-open the view. You should be able to copy/paste within the view now.