Courtney, The indenting after dragging is normal behavior. If you multiple levels of indenting, this can give confusing results. The original level of indent for the dragged section has no effect – it is only the level of indenting of the destination that matters. Generally the level of indent after dropping will be one level below the preceding summary task of the destination. An exception to this is if the preceding summary task of the destination is collapsed, in which case the dragged/dropped section will be at the same level as that preceding summary task.
I don’t know about the sequencing issue. As Larry and Daryl suggest, look at configured sorts in the view or at possible corruption of the view. If tasks are being shown in a completely different section of the RBS from their natural section, it sounds like the Sort option ‘Keep Outline structure’ is unchecked.