Reply To: counting the number of predecessors

Home Forums Discussion counting the number of predecessors Reply To: counting the number of predecessors

#410202
James Martin
Member

Using Project Pro 2013 stand alone. My solution took me down this path & revised formula.

IIf(LEN([Predecessors])>0;LEN([Predecessors])-LEN(REPLACE([Predecessors];’;’;”))+1;0)

Try that one… It appears to be a syntax issue, replace comma with semi colon and double quotes with single quotes. Original logic is correct.