Loading...
Quick Links

Reply To: Project Server Updates Using Durations Not Hours

Home Forums Discussion Project Server Updates Using Durations Not Hours Reply To: Project Server Updates Using Durations Not Hours

#410211
Larry ChristofaroLarry Christofaro
Participant

Brian, Daryl gave you a good option if you are and need to continue working with the timesheet. You also have other options if you use the task sheet. You have additional duration fields that can be updated by the user. Note that these duration fields are assignment duration, but I think you can get them to work like task duration if you do it right…such as (1) one resource per task, (2) don’t use Fixed Duration tasks, and (3) setup the projects and task sheet view in a consistent manner. It has a lot of configuration considerations, like the timesheet, so doing some reading and testing in a development environment would be suggested. Good luck…