Reply To: Estimating timeline when subtask duration is entered in HOURS

Home Forums Discussion Estimating timeline when subtask duration is entered in HOURS Reply To: Estimating timeline when subtask duration is entered in HOURS

#410273
Sud Tiwari
Guest

Hi Graham,

That worked fine. Thanks very much. I missed Daryl’s comment about Work hrs column. When I replaced the ‘duration’ column with ‘work hrs’ column, it just worked absolutely fine. I was struggling with this for over a month.

Thanks again,
Sud