Mike,
Resource Type is a resource field. It’s available in Task views but it only shows data when you use a task view such as Task Usage. In a Task Usage view, Resource Type is populated for each resource assigned to the task. But you’ll also notice that even in a task usage view, Resource Type does not populate at the task level. That’s because Resource Type is not applicable at the task level. Hope that helps.