Hey Darrell;
Creating the EPT by itself is a very simple process that takes about 10 minutes. The real time is involved in creating the PDP pages and the schedule template.
PDP pages are used to allow updates to Project level fields/codes. Some codes, such as multi-line text fields can only be updated from a PDP page. So the real question is how many project level codes/fields, how do they need to be organized, and are there any fields that can only be updated by specific people, and are there any fields that are specific to only one EPT? Basically, all the design considerations that feed into how many individual PDP pages need to be created and in addition, which PDPs can be used by the new EPT.
The default schedule template for the EPT is much the same. What needs to be in the schedule template? Are there any mandatory scheduling coding or task level codes that must be in there, and so on.
Hope that helps