Reply To: MS Project 2013 Activities rearranging their placement in the schedule

Home Forums Discussion MS Project 2013 Activities rearranging their placement in the schedule Reply To: MS Project 2013 Activities rearranging their placement in the schedule

#410327
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Cheryl, Since you mentioned the order is mixed up or sorted after reopening the file, I doubt if there is any VBA macro code that sorts the tasks when the file is opened. Please check View > Macros > Visual Basic and double click the project name. If the editor displays any code to sort the tasks on Project Open event, please delete it.