Reply To: Reporting on Assignment Units in Project Server 2013

Home Forums Discussion Reporting on Assignment Units in Project Server 2013 Reply To: Reporting on Assignment Units in Project Server 2013

#410397
Larry Christofaro
Participant

Paul, I believe the first issue is that the allocation % is not baselined. The second problem is that assignment units is not stored in the reporting database, only peak units. My only suggestion is to reverse engineer the % from the capacity and work values. Hope that helps.