Reply To: Reporting on Assignment Units in Project Server 2013

Home Forums Discussion Reporting on Assignment Units in Project Server 2013 Reply To: Reporting on Assignment Units in Project Server 2013

#410437
Larry ChristofaroLarry Christofaro
Participant

Paul, I’m pulling this out of memory so I apologize if it’s not completely accurate. A simple division would be a lot easier than to try to get the capacity from the resource capacity tables (you’ll at least get close). I do believe the data is in minutes, so using 480/day might get you a more accurate number.

Building a report in Excel might be hard given the amount of data in these by-day tables. Power BI (not to throw another wrench in the cog) might help if you are having trouble. Good luck…