Reply To: Subproject and Master project deadline problem. (with MS Project 2013)

Home Forums Discussion Subproject and Master project deadline problem. (with MS Project 2013) Reply To: Subproject and Master project deadline problem. (with MS Project 2013)

#410447
Larry Christofaro
Participant

Bob, I was able to reproduce the behavior you documented. Looks like a bug to me, but possibly with the deadline…not the sub-project. If I remove the deadline from the milestone, the links behave as expected. Give that a try and let me know what you get.