Reply To: Subproject and Master project deadline problem. (with MS Project 2013)

Home Forums Discussion Subproject and Master project deadline problem. (with MS Project 2013) Reply To: Subproject and Master project deadline problem. (with MS Project 2013)

#410449
Larry Christofaro
Participant

Bob, yes you can use one of the date fields instead of the deadline. You could test the dates and then use a graphical indicator to display an image. You could even set yellow for a warning and red when it is delayed. It’s still a bug, but the workaround might work well depending on your needs. Good luck…