Reply To: Corresponding Task Level Custom Field to Project level Custom Field

Home Forums Discussion Corresponding Task Level Custom Field to Project level Custom Field Reply To: Corresponding Task Level Custom Field to Project level Custom Field

#410593
Larry Christofaro
Participant

Naser,
The specific answer to your question is no, but the question back is why? You can include the project level Project Sponsor field with your tasks in a report. You can create a Power Pivot model in Excel or use Power BI, or other options…but you can include it by linking the Project ID. Anyway, good luck with your need.