Paul,
You can see the task information (including dates) for the predecessors and successors when you double click on them in the predecessors & successors detail view. I prefer to use the trace macro, which sets flag 5 to yes for predecessors/successors. Then sort by start or finish and you can see the flow of activities with dates/durations, etc. Hope that helps!
Tim