I did drop, could not wait to try it. And these are the results:
– I was quite disappointed it has to be developed both at a project level and at the masterschedule level. It will take some time to copy paste the fields with the organizer for all inflight projects but still worth it. And for new ones, this fields will be embedded in templates, so nothing to worry about
– You were right, once in the masterschedule you need to expand the summary project line for the values to appear; it is like a refresh thing. Again it worth it to expand all and then outline back at correspondent level once every morning to get those values
As a conclusion: it does work and is a very useful tool when working with several projects
A pleasure gents!