Reply To: Depicting column with finish date for specific activity in summarized projects

Home Forums Discussion Depicting column with finish date for specific activity in summarized projects Reply To: Depicting column with finish date for specific activity in summarized projects

#410672

Sergio
Glad it works! One quick thought. You might be able to quickly expand and collapse all the schedules in a couple mouse clicks. Click the Task Name column heading to select the entire column. In the View ribbon, click the drop down arrow on the Outline icon in the Data group. From that popup menu, select Hide Subtasks, and then from the menu a second time select Level 1. That should expand every schedule and then collapse down to the subproject level in two clicks!