Loading...
Quick Links

Reply To: Calendar for a 12 hour Rotating Shift

Home Forums Discussion Calendar for a 12 hour Rotating Shift Reply To: Calendar for a 12 hour Rotating Shift

#410703
Larry Christofaro
Participant

David, I’m not sure what you are doing with the one day each week, but try this and see if it makes sense. Create two exceptions with start dates one week apart. For each exception, select the Details tab, set them up as weekly for every two weeks with the appropriate days off, and an end date that goes past the end date of the project. I’m not sure what you are doing with the one day but it can be set individually for each week if you set them up as a daily exception. Hope that helps…