I wouldn’t create a Project-style plan for this. I’d focus on making sure the list is always in priority order and contains well-defined tasks and a clear statement of what constitutes “this task is complete”. Then I’d explain the rules to the team and let them go to work.

What value would you get from building the type of plan you describe?