I don’t work that much with the SharePoint task list but had a thought on at least part of your question. I’m not sure you can easily add columns to the task list (at least not out of the box). One thought on the calendar is that you could filter the calendar list to only tasks that have an assignment. Assigned not equal to (leave blank). Assumptions are that PMs aren’t assigning resources to summary tasks (a tried and true best practice) and that the assigned tasks are the more important tasks for the calendar. Other filters might work depending on what you want to display. Hope that helps…