Jigs GatonJigs Gaton
Member
  • Author
  • Forum Pro

Sebastian, first I think you should create a master plan with both projects included (subProject 1 & 2), and also use a shared resource pool for the master plan. Then you have to assign the work in hours, to each task, by resource. Remember, work can be independent of duration in MS project. To enter work independent of duration, use the task details form, and enter work (in time) for each resource assigned that task. Don’t use “Units.” Everything else should be automatically adjusted if the task mode for these tasks are set to “Auto Scheduled.” I am assuming that your processes are entered as tasks, and the duration of the task = the duration of the process. Best of luck,
Jigs