Reply To: Setting Reverse Task Links (Project 2013)

Home Forums Discussion Setting Reverse Task Links (Project 2013) Reply To: Setting Reverse Task Links (Project 2013)

#410919
Thomas Boyle
Guest

In the absence of a true Zero-Free-Float milestone in MSP, I typically handle this with a ready-for-FAT milestone.
i.e. (predecessors in parentheses)
1 – All physical activities up to and concluding with the driving predecessor of FAT.
2 – Ready for FAT (1 FS)
3 – FAT Notification (2 FS-14d)
4 – FAT (2 FS, 3 FS)

If contract absolutely prohibits start of FAT until 14d after notification, then the “3 FS” becomes “3 FS+14d”.