Why not create the FAT notification task as predecessor of FAT with a negative lag?
EG
1 FAT prep 15 days Mon 18 Sep Fri 06 Oct
2 FAT 1 day Mon 09 Oct Mon 09 Oct 1
3 FAT notification 0 days Tue 19 Sep Tue 19 Sep 2SS-14 days