Reply To: Difference between Relationship (dependency) and Constraints

Home Forums Discussion Difference between Relationship (dependency) and Constraints Reply To: Difference between Relationship (dependency) and Constraints

#410968

Terri
MS Project will automatically create a constraint when the PM manually enters (or selects) a task start or finish date. Because the PM enters it, Project see’s that as the same as entering a constraint.