Reply To: Shared Base Calendar (similar to Shared Resources via Resource Pool)

Home Forums Discussion Shared Base Calendar (similar to Shared Resources via Resource Pool) Reply To: Shared Base Calendar (similar to Shared Resources via Resource Pool)

#410975
Larry Christofaro
Participant

Jerry, great question and off the top of my head I can’t think of an answer to your “exact” request. But, what you can do is to create a common calendar to use when creating any new project. Try this. Search online for specific federal holiday rules , like Presidents Day is 3rd Monday in February and Christmas is 12/25. Then create a calendar that goes out a ways into the future (mine goes out to 2025). Start with entering the holiday for 2017, then go into details and setup the recurrence rule to the end date. This works for all holidays except those on specific dates (Christmas, New Year, Independence, etc.) You then create a special “Holiday observed yyyy” for those exceptions. Independence day 2020 is an example. Once it’s created, go to your organizer and replace your Global calendar with the calendar you just created. Going forward, every new project will be preset with your organization’s calendar. Hope this helps…