Reply To: 99% completed project when all tasks are 100%

Home Forums Discussion 99% completed project when all tasks are 100% Reply To: 99% completed project when all tasks are 100%

#411057
Alan JK
Guest

I’ve fixed this. I removed the allocation of resource at the top level and only applied resources at each individual task – as soon as I removed the resource at the top level the value when to 100 % and the Actual Finish date populated correctly.