Reply To: Budgeted cost progress

Home Forums Discussion Budgeted cost progress Reply To: Budgeted cost progress

#411104
fred
Guest

Dear Daryl,

You got exactely my point. The problem is that occuring the cost on task start or finish will give you something wrong in a planned cash-out, for example for a planning permission the payement can be at the end of the task, but not for a long task(for example HVAC fitting) in a master schedule.
I found another option which is to not let project calculate the actual cost.
I will try.

Many thanks